By George Kolar

|

|

October 19, 2026

What Happens if Your New Construction Home Is Late?

A builder contract gives an estimated completion date, not a guarantee. What a delay actually costs you, and what to ask for first.
Partially framed house standing quiet and unfinished on an empty lot under an overcast sky, with no crew working

What Happens if Your New Construction Home Is Late?

Usually less than buyers expect. A builder contract normally gives an estimated completion date rather than a guaranteed one, allows the builder to extend it for weather, labor, materials and permits, and limits your remedy to getting your deposit back. The costs a delay creates, temporary housing, storage and a lost rate lock, are typically yours.

The reason this surprises people is that they are comparing it to a resale purchase, where the contract works very differently.

Questions this guide answers:

  • Is the completion date in a builder contract actually binding?
  • Can I cancel if the builder is late?
  • Will the builder pay for my temporary housing?
  • What happens to my rate lock?
  • What if I already sold my current home?
  • Does a force majeure clause really cover everything?
  • What should I negotiate before I sign?

George Kolar and Chicago Suburb Living have specialized in Chicago suburban 55+ and active adult real estate since 2005. George holds the ABR and SRES designations and works across DuPage, Kane, Kendall, Will and McHenry counties, where most of the region's new construction is being built.

New Construction Homes in the Chicago Suburbs

How the Illinois Attorney Review Period Works

You Are Not on the Contract You Think You Are

This is the root of nearly every surprise in a new construction delay.

A resale purchase in the Chicago suburbs normally uses the Multi-Board Residential Real Estate Contract, a form drafted jointly by boards and bar associations with both sides in mind. New construction does not use it. You sign the builder's own contract, drafted by the builder's attorney, and it allocates risk accordingly.

That is not a scandal. It is normal, and it is also why the attorney review period matters more here than on any resale you will ever do.

Resale (Multi-Board) Typical Builder Contract
Closing date A specific date both parties commit to An estimated completion date, often a window
If the date slips Both sides negotiate, with defined remedies The builder usually has a contractual right to extend
Your remedy if it slips far Defined in the contract Frequently limited to return of your deposit
Your delay costs Negotiable between the parties Usually disclaimed by the builder
Time is of the essence Commonly present Commonly absent

Read that last row twice. The absence of a "time is of the essence" clause is not a drafting oversight. It is the point.

Estimated Is Doing a Lot of Work in That Sentence

When a sales representative says the home will be ready in May, that is a projection based on the current schedule. What the contract says is usually different, and the contract is what governs.

Typical builder completion language includes some combination of:

  • An estimated completion date rather than a firm one
  • A right to extend for weather, labor shortages, material delays, permit and inspection timing, and utility connections
  • A force majeure clause covering events outside the builder's control
  • An outside date, sometimes, after which you may terminate
  • A limitation of remedies, commonly return of deposit and nothing more

Ask for the outside date specifically. If the contract has one, you know the worst case and can plan around it. If it does not, you are agreeing to a schedule with no floor, and that is worth knowing before you sign rather than in month nine.

Force Majeure Is Narrower Than It Sounds

Buyers often read a force majeure clause and assume it means the builder can do whatever it likes. Illinois law is less generous than that.

Illinois courts construe these clauses narrowly and enforce them according to their actual wording. The question is whether the delay was directly caused by an event the clause names, not whether something inconvenient happened. A clause listing severe weather and government action is about severe weather and government action.

Illinois courts have also drawn the line in places buyers might not expect. Difficulty or economic loss alone does not excuse performance, and a force majeure clause generally displaces the common law doctrine of impossibility, which means an event the clause does not mention can be harder to rely on rather than easier.

The practical consequence is simple. Read the list. A clause that names specific events is more predictable than one with broad catch-all language, and the difference between them is worth raising during attorney review.

What a Delay Actually Costs You

The deposit is rarely the real exposure. These are.

Cost Why It Hurts
Rate lock expiry Extensions cost money, and a lock that expires into a higher market can change your payment for thirty years
Temporary housing Short-term rentals are priced accordingly, and some require a longer minimum term than you need
Storage Monthly, plus loading and unloading twice
Moving twice Two moves instead of one, and the second one happens on the builder's schedule
Selling first If your current home closed on time, you need somewhere to live for an unknown period
Carrying two properties If you did not sell first, you are paying for both longer than you planned

The rate lock is usually the largest number. Locks are written for a defined period, and a to-be-built home may take longer than any ordinary lock covers. Some builders offer extended locks through their affiliated lender, which is one of the genuine advantages of that route, and it is worth asking what happens if the build outruns even the extended period.

Builder Incentives and Rate Buydowns: What They Are Actually Worth

If You Have a Home to Sell

This is where a delay turns from an inconvenience into a genuine problem, and it is the most common version of the story in this market.

Downsizers and move-up buyers usually need the equity from the current home to close on the new one. That creates a sequencing problem that a delay makes worse in both directions: sell too early and you are housed somewhere temporary at your own cost, sell too late and you are carrying two properties.

Three ways people handle it, each with a real tradeoff:

  • Sell with a post-closing possession agreement. You close on your current home and stay in it for a defined period. It buys weeks, not months, and the period is fixed while the build is not.
  • Buy first using a bridge loan. Removes the timing problem and adds cost and qualifying complexity.
  • Sell, then rent short term. The most flexible and usually the most expensive, with two moves and storage.

Whichever you pick, build the delay into the plan rather than the best case. A buyer who assumed the May date and arranged everything around it has no slack when May becomes August.

How to Buy a Home While Selling Your Current Home

Post-Closing Possession in Illinois

Bridge Loans in the Chicago Suburbs

What to Negotiate Before You Sign

All of this is far easier to address during attorney review than after a delay is underway. A builder will not rewrite its contract, but specific requests on specific points are sometimes accepted, particularly on a home that is not yet started.

  1. An outside date with a right to terminate and a full deposit refund if it passes
  2. Written notice requirements, so you learn about a slip on a schedule rather than when you call to ask
  3. A rate lock extension provision, or a stated contribution toward extension costs if the delay is the builder's
  4. A per diem after a defined number of days past the outside date
  5. Clarity on what the force majeure clause actually covers, ideally a named list rather than a catch-all
  6. What happens to your deposit and your paid upgrade selections if you terminate
  7. Whether the price can change if costs move during an extended build

Even where the builder declines, you learn how it answers, and that is information. A builder that will not put an outside date in writing is telling you something about its schedule confidence.

Which New Construction Upgrades Are Worth It

While the Build Is Underway

Four habits that make a delay less damaging if one arrives.

Get the schedule in writing monthly. Not a phone call. A written update creates a record of what you were told and when, which matters if the dates keep moving.

Visit and photograph. Dated photos at framing, drywall and finish establish where the build actually was at each point. They help with warranty questions later too.

Keep your lender informed. Your loan officer can only manage a lock they know is at risk. Tell them the moment a date moves.

Do not give notice on your rental or list your home around the first projected date. Wait for drywall at minimum. Framing is not a schedule; it is an optimistic one.

New Construction Inspections and Warranties in Illinois

Frequently Asked Questions

Is the completion date in a builder contract binding?

Usually it is an estimate rather than a firm commitment. Builder contracts typically allow extensions for weather, labor, materials and permitting, and often omit a time-is-of-the-essence clause, which is standard in resale contracts.

Can I cancel if my new construction home is late?

Only if the contract gives you that right, usually through an outside date. Without one, there may be no point at which lateness alone lets you terminate. Ask whether an outside date exists before signing.

Will the builder pay for my temporary housing?

Generally not. Builder contracts commonly disclaim responsibility for delay costs, so temporary housing, storage and a second move are typically the buyer's expense unless the contract says otherwise.

What happens to my rate lock if the build runs long?

Locks run for a defined period and extensions usually cost money. If the lock expires and rates have risen, the new rate applies. This is often the largest single cost of a delay.

Do I get my deposit back if I walk away?

It depends entirely on the contract and on why you are walking. Terminating under a contractual right is different from walking away without one, and paid upgrade selections are often treated separately from the base deposit.

Does a force majeure clause cover anything the builder wants?

No. Illinois courts construe these clauses narrowly and apply them according to their wording. The delay generally has to be caused by an event the clause actually names, and economic difficulty alone does not excuse performance.

Should I sell my current home before the new one is finished?

Plan for the delay rather than the projected date. Post-closing possession, a bridge loan and a short-term rental each solve part of the problem and each carries a cost. Decide which tradeoff you prefer before you list.

When is it safe to schedule my move?

Most buyers wait until drywall is complete before committing to dates. A framed house can still move several weeks; a finished one usually cannot move much.

Can I ask for a per diem if the builder is late?

You can ask, during attorney review and before signing. Some builders accept a per diem after a defined number of days past an outside date. Asking after a delay has begun is much harder.

Does the implied warranty of habitability help with a delay?

No. That protection concerns latent defects in the construction itself, not the schedule. Timing is purely a contract question.

What if the price goes up during an extended build?

Check whether the contract allows price adjustments for cost increases. Many do not, but the ones that do make this a question you want answered before signing rather than after.

Is a quick move-in home safer?

On timing, yes. A home that is already built or nearly built carries far less schedule risk than a to-be-built one, which is part of why its incentives are often structured differently.

Should an attorney review a builder contract?

Yes. It is the builder's document, drafted by the builder's attorney, and the completion, extension and remedy clauses are exactly what the Illinois attorney review period exists to examine.

What is the single most useful thing to ask for?

An outside date with a right to terminate and a full deposit refund. It converts an open-ended schedule into a bounded one.

Why Work With George Kolar and Chicago Suburb Living

The builder's sales representative works for the builder. That is the arrangement, not a criticism, and it is why having your own representation costs you nothing and changes which questions get asked before you sign.

George Kolar has worked in Chicago suburban real estate since 2005, has helped more than 350 clients buy and sell homes, and holds the ABR and SRES designations. His practice covers DuPage, Kane, Kendall, Will and McHenry counties.

If you are considering a to-be-built home, George can help with:

  • Reading the completion and extension clauses alongside your attorney
  • Which requests builders in this market have actually accepted
  • Sequencing the sale of your current home against an uncertain finish date
  • Comparing a to-be-built home against finished inventory and nearby resales
  • Keeping a written record of schedule commitments as the build goes

New Construction vs Resale for 55+ Buyers

Can You Still Close on New Construction by Year End?

Learn More About George Kolar and Chicago Suburb Living

Final Thoughts

Most new construction finishes close enough to schedule that none of this matters. The problem is that you cannot tell in advance which build will be the exception, and the protections have to be in place before you sign.

So ask the three questions that decide how a delay goes: is there an outside date, what does the force majeure clause actually list, and who pays if my rate lock expires.

Buyers who ask those before signing rarely end up with a bad story. Buyers who rely on the date on the brochure sometimes do.

New Construction in Oswego, IL

Naperville New Construction Neighborhoods to Watch

Moving During an Illinois Winter

Browse Chicago Suburban 55+ Communities

Search Current Chicago Suburban Listings

Contact George Kolar

George Kolar, ABR®, SRES®
Chicago Suburb Living | Brokered by eXp Realty
630-479-1400
George@ChicagoSuburbLiving.com

This article is provided for general information and is not legal or financial advice. George Kolar is a licensed REALTOR and is not an attorney or a lender. Builder purchase agreements vary significantly between builders, communities and phases, and completion, extension, force majeure and remedy provisions differ in every contract. Nothing here describes the terms of any particular agreement. Review your specific builder contract with a licensed Illinois real estate attorney before signing, and confirm rate lock terms with your lender.

Share this Post:

Seniors Real Estate Specialist

George Kolar, SRES

I’ve helped clients buy over 300 homes in 55+ Communities since 2005. My clients say, “Moving to a 55+ community was one of the best decisions we’ve ever made. Our only regret is waiting so long—we wish we had started enjoying this lifestyle years sooner.”
George Kolar

George Kolar

630-479-1400

George@ChicagoSuburbLiving.com

eXp Realty

More From the Blog

Chicago Suburb Living

Questions About Your Own Move?

Ask about a specific suburb, a community, or what your current home would sell for today. George Kolar will get back to you personally.

Contact George Kolar, SRES