Can You Close Before Your New Construction Home Is Finished?

The driveway is not poured and closing is Monday. Two rulebooks let you close anyway, on two deadlines that do not line up.

George Kolar

By George Kolar, ABR®, SRES®

13 min read

A newly built suburban house with finished siding and windows, no driveway poured, bare dirt and construction stakes where the front yard would be, on an overcast late autumn day.
The house is done. The yard is the part that decides your closing.
On This Page
  1. Two Separate Permissions, Two Separate Clocks
  2. What the City Requires: Naperville as the Example
  3. What the Lender Requires: The 120% Holdback
  4. The Two Deadlines Do Not Line Up
  5. The Punch List Is Not the Holdback
  6. Why This Matters This Month
  7. What to Get in Writing Before You Close
  8. Frequently Asked Questions
  9. Final Thoughts

The Short Answer

Usually yes, and in an Illinois November it is common. It takes two separate approvals: a temporary certificate of occupancy from the municipality, and a completion escrow from your lender that holds back money for the unfinished work. They are granted by different parties, on different conditions, with different deadlines, and most buyers do not learn that until the week of closing.

What This Guide Answers

  • Can you legally move into a home that is not finished?
  • What is a temporary certificate of occupancy, and how long does it last?
  • What is an escrow holdback, and how much money does the lender keep?
  • Who decides when the driveway and the sod have to be done?
  • Is the punch list the same thing as the holdback?
  • What happens if the work is never finished?

How these numbers were gathered: George Kolar and Chicago Suburb Living have specialized in Chicago suburban real estate since 2005, including Lennar and Pulte new construction across Naperville, Plainfield, Aurora, Oswego, Joliet and Shorewood. Late-fall closings on homes with outdoor work left to do are routine here, and they are also where the paperwork surprises live.

01Two Separate Permissions, Two Separate Clocks

When your closing date arrives and the driveway has not been poured, two different institutions have to agree to proceed, and neither one cares much about the other's rules.

The municipality controls whether anyone may legally occupy the building. That is the certificate of occupancy, and it is issued by the village or city, not by the builder and not by your lender. If the home cannot get a final certificate, the question becomes whether it can get a temporary one.

The lender controls whether the loan can fund and be sold. Most conventional loans are written to be sold to Fannie Mae, so Fannie Mae's rules govern in practice even though you never meet them. Those rules permit funding before the work is done, but only on specific conditions and only with money held back.

Two approvals, two sets of conditions, two deadlines. A buyer who gets one and assumes the other is handled is the buyer who ends up rescheduling a moving truck.

02What the City Requires: Naperville as the Example

Certificate of occupancy rules are municipal, so they differ from town to town, and the only version that governs your home is the one for the municipality it sits in. Naperville publishes its process clearly enough to use as a worked example, and it is a town where this comes up often enough to matter: see Naperville new construction neighborhoods and why Naperville new construction appeals to buyers. The figures below come from the City of Naperville Temporary Occupancy Request packet, form revised August 2024, read on November 5, 2026.

ItemWhat Naperville Requires
Who it is forOwners of new or substantially improved single-family homes, duplexes and townhomes who want to occupy before completion
Condition of the homeInterior work completed, with only a few minor exterior items left. An inspector must certify the property is substantially complete and eligible
ApplicationSigned and notarized, submitted to Inspection Dispatch after a scheduled final inspection
Deposit0.50% of the value of the improvements, with a $2,000 minimum, based on the valuation on the permit
GradingA professional engineer's statement certifying final grading was completed in substantial conformance with the approved site plan, or a topographical survey
Normal termUp to 60 days from issuance
Cold-season termIssued between October 1 and April 15, it may be extended to June 15
Deposit refundRefunded in full when the final certificate of occupancy is issued
ForfeitureIf no final certificate is issued within 24 months of the temporary one expiring, the deposit is forfeited
Occupying without oneA fine of up to $500 per day of unlawful occupancy

Three things in that table are worth pulling out.

First, the cold-season extension is the whole reason this works in November. A temporary certificate issued today would normally expire in early January. Because it falls inside the October 1 to April 15 window, it can run to June 15, which is roughly when concrete and sod are workable again in this market. The ordinance is written around the Illinois construction season.

Second, final grading is called out specifically and separately. Naperville wants an engineer's statement on the grading, which means grading is not one of the items you can simply defer and sort out in spring. Drainage affects the neighbors, so it gets its own requirement.

Third, the deposit is the builder's money, not yours, in the ordinary case, because on a builder deal the builder holds the permit and applies for the certificate. Confirm who is applying and who is posting it, because if anyone asks you to fund it, that is a term you should see in writing before closing.

One inconsistency in Naperville's own documents, for whatever it is worth at the counter: the instruction sheet asks for a check while the application form says cash deposit. Call 630-420-6100 and ask which they want. And because these forms are revised periodically, confirm the current figures with the city rather than with this article.

03What the Lender Requires: The 120% Holdback

The lender side is more uniform, because most conventional loans follow the Fannie Mae Selling Guide. The relevant section is B4-1.2-05, Requirements for Verifying Completion and Postponed Improvements, carrying a page date of December 10, 2025 and read on November 5, 2026.

The default rule is that the work is supposed to be done: improvements, alterations and repairs are generally required to be complete when the loan is sold. The exception, which Fannie Mae calls postponed improvements, is what makes a November closing possible.

RequirementWhat the Selling Guide Says
Deadline to finishWithin 180 days of the note date
Valid reasons to postponeItems postponed for a valid reason, with inclement weather and a shortage of building materials given as the examples
Must be in the contractThe postponed items have to be part of the sales contract. Third-party contracts are not permitted
Occupancy limitThe postponed items must not affect the ability to obtain an occupancy permit
Size limitThe cost to complete must not exceed 10% of the "as completed" appraised value
Money held back120% of the estimated cost to complete, withheld from the purchase proceeds
Exception to the 120%If the builder gives a guaranteed fixed-price contract for the work, the escrow only needs to equal the full contract price
PaperworkA signed escrow agreement stating how the account is managed and how funds are disbursed
TitleA final title report showing no outstanding mechanics liens and taking no exceptions to the postponed work or the escrow agreement. If title issues before the work is done, an endorsement protecting lien priority is required
ReleaseAfter a satisfactory completion report, the lender releases the final draw, including anything left over

Completion is proven with an Appraisal Update and Completion Report, Form 1004D, or an approved alternative. Fannie Mae now also allows a letter signed by both the borrower and the builder certifying the home was built in conformity with the plans, specifications, amendments and change orders, with interior and exterior photographs attached. If a jointly signed letter cannot be obtained, the appraiser's Form 1004D is required.

Note the interaction with the occupancy permit, because it is the hinge of the whole arrangement. The lender will escrow for work that does not block the occupancy permit. The city will issue a temporary permit when only minor exterior items remain. Anything substantial enough to block occupancy is not escrowable and not deferrable. It has to be finished.

Two limits on everything above. These are conventional loan rules; FHA, VA, USDA and portfolio lenders set their own, and some decline holdbacks entirely. And a lender may be stricter than the guide allows, because the guide sets a floor rather than a ceiling. Ask your loan officer whether they do completion escrows at all, and ask early.

04The Two Deadlines Do Not Line Up

Here is the arithmetic nobody runs until it matters. Take a buyer closing on November 30, 2026, which is the funding deadline on Lennar's current Chicago promotion.

Fannie Mae's clock starts on the note date and runs 180 days, so the work has to be complete by roughly May 29, 2027. Naperville's temporary certificate, issued inside the October 1 to April 15 window, can run to June 15, 2027. The city would still be satisfied on May 30. The lender would not.

That gap is small and it runs the direction most people would not guess: the lender's deadline is the tighter one, not the city's. In practice it means the spring punch-out has to be scheduled against the note date, not against the municipal expiration, and that a builder promising work "in the spring" has committed to something vaguer than either deadline. Ask for a month.

A second timing trap sits in the escrow release. The money comes back after the completion report is accepted, not when the builder says the job is done. Build in time for the appraiser or for the signed completion letter and photographs.

05The Punch List Is Not the Holdback

These get conflated constantly, and they are different instruments with different enforcement.

The punch list is contractual. It comes out of your walkthrough with the builder, often called the orientation or the blue-tape walk, and it lists the paint scuffs, the sticking door, the missing switch plate, the scratched countertop. It binds the builder because the contract says so. No lender and no municipality is holding money to make it happen.

The escrow holdback is a lending instrument. It covers work the lender agreed to let you close without, and the leverage is the money sitting in the account.

The practical consequence: a long punch list and an empty holdback leaves you relying on the builder's goodwill and the warranty. So get the punch list signed and dated by someone with authority before you close, keep your own photographed copy, and understand which items are punch list and which are inside the escrow. If a punch list item is also a warranty item, submit it through the warranty channel as well so there is a record in both systems.

Behind both of those sits the implied warranty of habitability, which Illinois courts recognize on new residential construction and which builders frequently ask buyers to waive in the contract. That is covered in our guide to new construction inspections and warranties, and it is worth reading before you sign anything that disclaims it.

06Why This Matters This Month

Two things make this live right now rather than theoretical.

The first is the weather. Final grading, driveways, flatwork, sod and landscaping are the items that stop being practical in a Chicago-area November, and they are exactly the items that end up postponed. Interiors keep moving; the yard does not.

The second is the calendar. Lennar's Chicago promotion, read off its own promotion page on November 5, 2026, requires a purchase agreement signed between 11/02/26 and 11/08/26 and a closing by 11/30/26, with a promotional 7/6 adjustable rate mortgage at 3.500% with a 6.964% APR in year one, 4.500% with the same APR for years two through seven, and up to $5,000 toward closing costs. The offer requires financing through Lennar Mortgage, LLC, and the page states that limited funds are available. That signing window closes Sunday.

It is worth knowing which homes are even in range for a November 30 funding date. Only a finished home can close that fast, which is why the current Lennar and Pulte move-in-ready inventory is where these deals land, and why the prices on those listings move daily.

Put those together and the shape of the risk is clear. A promotion that forces a November 30 closing, on a home in a market where outdoor work cannot be completed in November, is a promotion that makes temporary occupancy and completion escrows part of the deal rather than an edge case. That is not a reason to avoid it. It is a reason to ask about both before you sign, while you still have leverage. Our breakdown of the deadlines inside that Lennar offer and of whether you can still close by year end cover the timeline from the other direction.

07What to Get in Writing Before You Close

  • Which certificate the home will have at closing, final or temporary, and if temporary, its issue date and expiration date.
  • The written list of postponed items, itemized, with a cost estimate for each and a completion month for each. "Spring" is not a date.
  • Whether the builder will give a guaranteed fixed-price contract for the postponed work. It is better for everyone: the escrow drops from 120% to the contract price, and your exposure to a cost increase disappears.
  • Who holds the escrow, what releases it, and who signs off. Ask for the escrow agreement before closing day, not at the table.
  • The signed, dated punch list, photographed, with the builder representative's name on it.
  • The title position on the postponed work, including whether an endorsement is being issued. Unfinished work and lien risk meet here: ask whether final lien waivers have been collected for the work already done, and what happens to the waivers for work still to come.
  • Your own final inspection, scheduled before closing. A municipal inspection is not a buyer's inspection and never has been.

And read the completion date language in the contract itself. Builders write it as an estimate, Illinois construes force majeure narrowly but the clause wording controls, and the remedies are usually thinner than buyers assume. That is the subject of what happens if your new construction home is late, and it pairs with whether your deposit is refundable in Illinois.

FAQFrequently Asked Questions

Can you move into a house without a certificate of occupancy?

No. Occupying a home with neither a temporary nor a final certificate is a code violation, and in Naperville it carries a fine of up to $500 per day of unlawful occupancy. If the home is not finished, the lawful route is a temporary certificate of occupancy from the municipality, not moving in anyway.

How long is a temporary certificate of occupancy good for?

In Naperville it is valid for up to 60 days from issuance, but one issued between October 1 and April 15 may be extended to June 15, which accommodates the Illinois construction season. Other municipalities set their own terms, so confirm the rule for the town your home is in.

What is an escrow holdback on a new construction closing?

It is money the lender withholds from the purchase proceeds at closing to cover work that is not finished yet. Under the Fannie Mae Selling Guide the amount is 120% of the estimated cost to complete, or the full contract price if the builder provides a guaranteed fixed-price contract for the work.

How long does the builder have to finish the postponed work?

On a conventional loan following Fannie Mae guidelines, postponed improvements must be completed within 180 days of the note date. The cost to complete also cannot exceed 10% of the home's "as completed" appraised value, and the unfinished items cannot be anything that would prevent an occupancy permit.

Is a punch list the same as a holdback?

No. A punch list is a contractual list of defects and unfinished details from your walkthrough with the builder, enforced through the contract and the warranty. A holdback is a lender escrow that retains money until specific postponed work is verified complete. One can exist without the other.

Can the builder make me close before the home is done?

The contract governs, and builder contracts commonly allow closing once a certificate of occupancy, including a temporary one, has been issued. Before you sign, ask what happens if only a temporary certificate is available on the closing date, and have an attorney read that provision with you.

08Final Thoughts

Closing on an unfinished home is normal, documented and survivable. What makes it go wrong is treating it as a single yes rather than two, and accepting "in the spring" as an answer to a question that two separate rulebooks answer with dates.

Get the certificate type and its expiration. Get the postponed items itemized with months. Get the fixed-price contract if the builder will give it. Then the holdback is a formality rather than the thing you are still arguing about in May.

More on this market: new construction homes in the Chicago suburbs, the Lennar Raleigh floor plan in Oswego, new construction in Oswego, what happens if the appraisal comes in low, and moving during an Illinois winter.

George Kolar

About the Author

George Kolar, ABR®, SRES®

Managing Broker, eXp Realty · Licensed Since 2005

The builder's sales agent represents the builder, the lender's job is to fund a loan it can sell, and the village inspector is enforcing a code. None of the three is responsible for noticing that the completion date in your escrow agreement lands two weeks after your lender's own deadline.

We work these closings in Naperville, Plainfield, Aurora, Oswego, Joliet, Yorkville and Shorewood every season, including the November and December ones where half the yard is still dirt. Representation on a builder deal costs you nothing in nearly every case, and it has to be in place before your first visit to the model.

Disclaimer: This article describes general practice and cites published documents as of the dates stated: the Fannie Mae Selling Guide section B4-1.2-05 and the City of Naperville Temporary Occupancy Request packet, both read on November 5, 2026, and Lennar promotion terms read the same day. Lender guidelines, municipal ordinances and builder promotions all change without notice, and certificate of occupancy requirements differ in every municipality. Nothing here is legal advice, tax advice or lending advice, and nothing here is a commitment to lend. Confirm the rules for your municipality with that municipality, confirm your loan requirements with your lender, and have your purchase agreement and any escrow agreement reviewed by your own attorney before you sign.