The Short Answer
Illinois does not require a seller disclosure report on a newly built home that has never been occupied. The statute exempts it outright. So on new construction there is no document telling you what is wrong with the house, and the builder's own walkthrough sequence is the only inspection the process gives you. What you sign at the end of it closes the door on cosmetic claims, but it does not waive the implied warranty of habitability. That waiver, if it exists, is in the purchase agreement you signed months earlier.
What This Guide Answers
- What walkthroughs does a builder actually give me, and when?
- What am I signing at the orientation, and what does it give up?
- Can I bring my own inspector?
- Can I refuse to close over an unfinished house?
- What does the ten-year structural warranty really cover?
- Why do people talk about an eleven month walk?
How these numbers were gathered: George Kolar and Chicago Suburb Living have specialized in Chicago suburban real estate since 2005. We covered hiring your own inspector and the warranty tiers in new construction inspections and warranties. This one is about the builder's own sequence: what each walk is called, what happens at it, and what the signature at the end is worth.
01Start Here: There Is No Disclosure Report
The Illinois Residential Real Property Disclosure Act lists the transfers it does not cover, and item nine is "transfers of newly constructed residential real property that has never been occupied." The Act adds that this "does not include rehabilitation of existing residential real property."
On a resale you get the seller's answers about the roof, the basement and the sump pump, as we described in the Illinois seller disclosure. On a brand-new house you get nothing of the kind. The walkthroughs are the substitute, which is why they deserve more attention than buyers usually give them.
02What the Builders Call Each Stage
Every national builder active in these suburbs uses its own vocabulary, and the terms do not line up. Here is what each one publishes on its own site.
| Stage | Pulte | Lennar | M/I Homes | D.R. Horton |
|---|---|---|---|---|
| Kickoff meeting | Introduction | Not published | Initial meeting | Not published |
| Walls-open walk | Pre-Drywall Orientation | Not published | Pre-Drywall Orientation | Frame Quality Inspection |
| Finish walk | Pre-Closing Orientation | New Home Orientation | New Home Orientation | Orientation |
| Sign-off walk | Celebration | Final Walkthrough | Final Walkthrough | Re-walk |
| Document signed | Sign off that the home is complete | Sign off on the list | Not published | Orientation Builders Checklist |
A term to retire: blue tape. None of these builders uses it anywhere on its own site. It is consumer and inspector slang, borrowed from the painter's tape people stick next to a flaw. Useful shorthand, but if you ask your construction manager to schedule "the blue tape walk" you may get a blank look.
Lennar publishes the most detail. Its New Home Orientation "will typically take place a week prior to the day you are scheduled to close," and "should last no more than two hours." Afterward you hand the construction manager a list of concerns, which the builder works through "during the 7 calendar days prior to your Final Walkthrough." The Final Walkthrough itself "typically lasts 30 to 45 minutes, and at the end, you will sign off on the list indicating your new home is complete."
Pulte describes four meetings with the construction manager, and M/I Homes schedules its pre-drywall walk "after mechanical rough-ins pass municipal code inspections," to let you view "wiring, plumbing lines, and structural framing before walls are sealed."
One Illinois Item to Check While the Walls Are Open
Illinois requires it and almost nobody looks for it. Under 420 ILCS 52/20, "all new residential construction in this State shall include passive radon resistant construction." The pre-drywall walk is the only time you will ever see that rough-in. Ask where it is and photograph it, then read radon testing in Illinois homes for what to do after you move in.
03Can You Bring Your Own Inspector?
Two of the five builders publish a policy, and both of them govern the end of the build rather than the pre-drywall stage.
Lennar says "you are welcome to have your new Lennar home inspected by a professional of your choice," that outside inspections "must be coordinated" with the builder, that the buyer pays, and that it "must be completed a couple of days prior to your New Home Orientation." If the report finds something, you "will be required to share a copy of the inspection report" with the builder "at least two days before the New Home Orientation."
M/I Homes, in its Austin materials, says third party inspectors may attend the orientation and that "any third-party inspections should be conducted 14 days prior to the NHO date."
Pulte, D.R. Horton and Ryan Homes publish no third-party inspector policy I could find, and no builder publishes one for the pre-drywall stage. So do not assume. Ask in writing, early, and get the answer before the drywall goes up.
04What That Signature at the End Actually Does
Two separate questions, and keeping them apart is the whole point of this section.
It Closes the Door on Cosmetic Items
This one is real and the builders say so plainly. D.R. Horton's own FAQ: damages such as "scratched glass, cuts in vinyl flooring, damaged countertops, drywall repairs and paint touch-ups are not warranted after closing. These items must be noted on the Orientation Builders Checklist and taken care of prior to closing." Landscaping too: trees, shrubs and grass "are not warranted after closing unless specifically noted on the Orientation Builders Checklist."
Pulte's warranty book applies the same cutoff to the driveway: "Unless noted on the final walk-through, any crack or chip in the masonry driveway is not covered under the Warranty."
Lennar's description of its own purchase agreement is the bluntest: "Failure to take advantage of the pre-closing inspection can forfeit the repair of certain items if later discovered. Likewise, certain items will not be repaired if not identified during the pre-closing inspection."
So the list you build at that walk is not a courtesy. It is the record, and anything cosmetic that is not on it is generally gone.
It Does Not Waive the Implied Warranty of Habitability
Illinois has protected new home buyers since 1979, when the Illinois Supreme Court decided Petersen v. Hubschman Construction. The court called the implied warranty "a judicial innovation of rather recent origin used to avoid the harshness of caveat emptor," reasoning that "the vendee has little or no opportunity to inspect" and "must rely upon the integrity and the skill of the builder-vendor." What the buyer is owed is "a house that is reasonably fit for use as a residence," and the warranty "extends only to latent defects."
It can be waived, but Illinois sets a deliberately high bar. Petersen held that a disclaimer "must be strictly construed against the builder-vendor." In 2001 the Illinois Supreme Court added the rule that catches most attempts: "any disclaimer that does not reference the implied warranty of habitability by name is not a valid disclaimer of that warranty." An Illinois appellate court later stated the full test: an effective waiver "is one that is a conspicuous part of the parties' agreement, refers to the warranty of habitability by name, and discloses the consequences of its inclusion."
An orientation checklist does none of those things. The waiver, where there is one, sits in the purchase agreement you signed months before the foundation went in. Pulte's national warranty book, for example, states that "all implied warranties of fitness, merchantability, or habitability, are disclaimed and excluded." That is the document to read, not the clipboard at the walkthrough.
One More Thing the Courts Have Settled
In 2018 the Illinois Supreme Court held that a buyer "may not pursue a claim for breach of an implied warranty of habitability against a subcontractor where there is no contractual relationship," overruling an older case that had allowed it when the builder was bankrupt. The court's answer to the bankruptcy argument was short: "The fact that a defendant may become bankrupt is a possibility faced by every civil litigant." If your builder fails, the trade who did the work is not your defendant.
05Can You Refuse to Close Over an Unfinished House?
Yes, and the case that says so is the same Illinois case, out of Lake County, that created the warranty.
The Petersens' house had a basement floor pitched away from the drain, improperly installed siding, a defective bay window, a bad front door and frame, and nail-popping drywall. The builder agreed to a punch list and did not deliver. The buyers proposed that he put $1,000 in escrow to guarantee the repairs. He refused. They refused to accept the house and no closing happened.
Crucially, the opinion records that "no one disputes that the house was at least habitable." The builder argued that because it was habitable the buyers had to close and sue for damages. The Supreme Court disagreed: substantial performance "was a constructive condition to performance by the Petersens," and "it would be manifestly unjust to require the Petersens to accept a house in which there were defects in substance in construction and to settle for damages. That is not what they had bargained for."
They won back their earnest money and their materials, about $19,000. Read the other half of that sentence too, though: whether a builder has substantially performed "is always a question of fact." Refusing to close is a right you assert and then defend, not a switch you flip, and the Petersens defended theirs all the way to the Illinois Supreme Court.
The Punch List Is a Promise. The Holdback Is Money.
Erica Minchella, an Illinois real estate attorney in Skokie, puts the practical problem well. Developers often get a certificate of occupancy before finishing, leaving "unfinished details like electrical covers, misaligned cabinets, or incomplete painting," captured in a punch list. Then: "The challenge? Making these fixes get completed after the sale. Reputable developers will agree to a holdback, where the lender holds a portion of the funds until all punch list items are resolved. Untrustworthy developers, however, will resist holdbacks, prioritizing their payment over finishing the job." She also notes that new construction contracts "are almost always slanted in favor of the developer" and are often contracts of adhesion.
Paul Garver of Hawbecker and Garver in Hinsdale, who served on the drafting committee for both the 7.0 and 8.0 versions of the standard Illinois contract, teaches other attorneys to define substantial completion in writing rather than argue about it later. His list: all mechanical systems in good working condition, all fixtures and appliances installed and working, doors and hardware installed, a finished coat of paint on all walls, trim, moldings and doors, all floors and floor coverings installed, all grading and landscaping complete, and all upgrades and contract selections installed.
That definition belongs in the contract, not in a conversation. On the money side, see is your new construction deposit refundable and, for the escrow mechanics, closing before the home is finished.
06Two Things to Get Right About the Warranty
The first is that "1-2-10" is not universal. Lennar publishes that structure by name: one year workmanship, two years systems, ten years structural. Pulte's national warranty book is 1-2-5-10, adding five years on "certain kinds of water infiltration and internal leaks." We compared the two builders more broadly in Lennar vs Pulte in the Chicago suburbs, and the warranty tiers themselves are covered in new construction inspections and warranties.
The second is how narrow the ten-year tier is. Pulte's own definition says a structural element "will not be deemed defective, and no action will be required of the Builder, unless there is actual physical damage that diminishes the ability of the Structural Element to perform its load-bearing function such that the home is unsafe." A cracked slab is not automatically covered. Read your builder's definition before relying on the number.
Running behind all of it is Illinois law at 735 ILCS 5/13-214, which gives four years from when you "knew or should reasonably have known" of a construction act or omission, with an outside limit of ten years from the act itself. That ten-year figure is a statute of repose, not a warranty term. You will see it described online as a "ten-year implied warranty of habitability." It is not. The warranty has no fixed term; the ten years is the deadline for bringing the claim.
07The Eleven Month Walk
Almost nobody among the big builders publishes one. The exception explains the idea. D.R. Horton's own warranty manual tells homeowners they "will have the opportunity to submit one Warranty Service Request, at the 11th month interval," and to "limit your warranty requests to an 11th month list."
Eleven, not twelve, because the one-year workmanship tier expires at twelve and you want the list filed with time to spare. Lennar's purchase agreement disclosure makes the stakes explicit: the builder "has no obligation with respect to claims submitted more than 30 days after the expiration of the applicable limited warranty."
Everyone else promoting the eleven month walk is an inspection company rather than a builder. That does not make it a bad idea. It makes it your idea rather than the builder's, and it needs to go on your own calendar at closing.
FAQFrequently Asked Questions
Does Illinois require a seller disclosure on a new construction home?
No. The Residential Real Property Disclosure Act exempts "transfers of newly constructed residential real property that has never been occupied." A rehabbed existing home is not exempt. On a never-occupied new build, the builder's walkthroughs are the only inspection the process provides.
What am I signing at the builder orientation?
A list confirming the condition of the home at that moment. D.R. Horton calls it the Orientation Builders Checklist; Lennar describes signing off on the list to indicate the home is complete. Cosmetic items not noted on it, such as scratched glass or damaged countertops, are generally not warranted after closing.
Does signing the orientation checklist waive the implied warranty of habitability?
No. Illinois requires a waiver to be a conspicuous part of the agreement, to refer to the warranty of habitability by name, and to disclose the consequences of waiving it. An orientation checklist does none of those. Any waiver sits in the purchase agreement signed before construction began.
Can I refuse to close on a new home that is not finished?
Illinois law allows it where the builder has not substantially performed, and a merely habitable house is not automatically a substantially performed one. That was the holding in Petersen v. Hubschman. But whether a builder substantially performed is a question of fact decided later, so this is a right with real risk attached. Talk to your attorney before you refuse.
Why do people schedule an eleven month walkthrough?
Because the one-year workmanship warranty expires at twelve months, and filing at eleven leaves time to submit the list. D.R. Horton builds this into its own procedure. Most other builders do not publish it, so it has to go on your own calendar at closing.
08Final Thoughts
A new Illinois home comes with no disclosure report and a stack of builder documents written by the builder. The walkthroughs are your only real look at the house, and the signature at the end of them is worth exactly what the purchase agreement says it is worth.
Three things to do, in order. Get the pre-drywall date in writing at contract. Put every cosmetic item on the orientation list, because the list is the record. And read the limited warranty and any habitability waiver before you sign the purchase agreement, not at the end.
More on buying new in these suburbs: read new construction inspections and warranties, what happens if your home is late, how attorney review works, and what the financing contingency protects.
Disclaimer: This article is general information about Illinois new construction practice and is not legal advice. George Kolar is a licensed Illinois REALTOR®, not an attorney. Builder procedures are quoted from each builder's own published pages read on November 13, 2026 and differ by division, by community and over time; several of the D.R. Horton and M/I Homes documents cited are published by divisions outside Illinois and may not describe local practice. No builder publishes its Illinois purchase agreement, so contract terms here come from Lennar's own public description of its agreement and from named Illinois attorneys. Case language is from the courts' published opinions. Your contract and your builder's warranty govern. Have an Illinois attorney review both.